Project Start Date: Thu 4/17/08
Project Finish Date: Mon 5/19/08
Name |
Start_Date | Finish_Date |
|---|---|---|
Aaron assemble gripper for Boe-Bot 2 |
Tue 4/15/08 | Wed 4/16/08 |
Shervin assemble gripper for Boe-Bot 1 |
Thu 4/17/08 | Fri 4/18/08 |
Shervin Design gripper movement assembly |
Fri 4/18/08 | Mon 4/21/08 |
Shervin make gripper movement assembly |
Mon 4/21/08 | Thu 4/24/08 |
Aaron program Gripper/Arm movements |
Fri 4/18/08 | Wed 4/23/08 |
Shervin and Aaron program Large body movements | Fri 4/18/08 | Tue 4/22/08 |
Aaron adjust gripper for grabbing Lego for Boe-Bot 1 |
Tue 4/22/08 | Thu 4/24/08 |
Aaron assemble base of rotating platform - did not use |
Mon 4/28/08 | Mon 4/28/08 |
Aaron and Shervin assembled and programmed digital encoder |
Tue 4/29/08 | Thu 5/8/08 |
Jacob redesigned base of rotating platform |
Thu 5/1/08 | Fri 5/2/08 |
Aaron Program stepper motor - did not use |
Thu 5/1/08 | Fri 5/2/08 |
Shervin repositioning gripper arm |
Thu 5/1/08 | Thu 5/1/08 |
Aaron create base of rotating platform |
Thu 5/1/08 | Thu 5/1/08 |
Jacob design and create an elevation actuator |
Sat 5/3/08 | Mon 5/5/08 |
Aaron write program for elevation actuator |
Sat 5/3/08 | Sun 5/4/08 |
Aaron program large body movements for Boe-Bot 2 | Tue 5/6/08 | Wed 5/7/08 |
Shervin write project section of Abstract |
Fri 5/9/08 | Mon 5/12/08 |
Jacob write design section of Abstract |
Sat 5/10/08 | Tue 5/13/08 |
Aaron write flowcharts for Boe-Bot 1 and 2 |
Sat 5/10/08 | Mon 5/19/08 |
Shervin write program for gripper movements |
Sun 5/11/08 | Thu 5/15/08 |
Aaron and Shervin work on PowerPoint presentation |
Tue 5/13/08 | Mon 5/19/08 |
Jacob and Aaron designed/build tread elivator and gripper extension |
Tue 5/13/08 | Mon 5/19/08 |
Jacob write conclusion and design section of abstract |
Tue 5/19/08 | Mon 5/19/08 |
Jacob, Aaron, and Shervin finish writing code and setting up track |
Tue 5/19/08 | Mon 5/20/08 |